ATLANTA – The State Transportation Board gave the go-ahead Thursday to a series of improvements along Georgia 316 between Lawrenceville and Athens to relieve traffic congestion and improve safety along the heavily traveled corridor.
Board members approved a joint resolution with the State Road and Tollway Authority (SRTA) to move forward on the first of three “bundles” of projects, a $100 million plan to build grade-separated interchanges at Georgia 316’s intersections with Bethlehem and Barber Creek roads in Barrow County.
The Georgia Department of Transportation will issue a request for proposals from interested contractors in July, Andrew Hoenig, construction program manager for the DOT’s Office of Alternative Delivery, told members of the board’s Program Delivery Committee on Wednesday.
The DOT will announce the apparent winner of the bidding in December and return to the board early next year for a notice to proceed with the work, Hoenig said. He said construction will start during the fall of next year,
“We’re looking at trying to grade separate some of the signalized intersections along the corridor,” he said. “You have a lot of conflicting movements now, with turns to the side roads, and you have a lot of bumper-to-bumper traffic.”
Hoenig said a second bundle of projects in Oconee County will build grade-separated intersections at the 316 intersections with Jimmy Daniel Road and the Oconee Connector. The contract for $150 million of planned improvements…