ATLANTA — Georgia’s energy regulators are considering Georgia Power’s request to generate and buy more electricity to meet what the utility calls a surge in demand from new businesses in the state. State lawmakers, meanwhile, are grappling with a leading source of that increased power demand: high-tech data centers.
Georgia Power says the spike in demand is so high and will be needed so soon that it needs to rapidly add sources of electricity to the grid, so it has filed an update to its long-range power plan, known as the Integrated Resource Plan, or IRP. The company is seeking approval to buy electricity from other utilities, build new gas and oil turbines at an existing power plant, and build new solar and battery storage.
The Gwinnett Daily Post is a daily newspaper published in Gwinnett County, Georgia, and serves as the county's legal organ. The newspaper is owned by Times-Journal Inc. and prints Wednesday and Sunday each week.